PROJECT 1:

Independent Monitoring Consultant of Public Private Partnership Project in Collection & Transportation of MSW in 6 MCD Zones, Project Cost- US$ 32.60 Million, Delhi, India

Consultant is responsible for discharging its function as Independent Monitoring Consultant for Public Private Partnership Project in Collection & Transportation of MSW in 6 MCD Zones & which is covering following main activities: -

• Verification and random checks of weighment and Testing of the MSW at the Landfill Site. In addition, the    representative of Independent Consultant has to keep watch on type of waste deposited and ensure that    only MSW is deposited at SLF Site.

• Independently review, monitor and where required by the Agreement, to approve the design, construction,    operation and maintenance of the Project Facilities to ensure compliance by the Concessionaire with the    Operations Plan, Design Requirements, Construction Requirements and O&M Requirements. The MSW rules    2000 lay emphasis on avoiding manual handing of MSW. The collection, storage and transportation of MSW    has to be done in closed containers.

• Report to the Parties on the various physical, technical and financial aspects of the Project based on    inspections, site visits and Tests. The Independent Consultant has to ensure that S. C. bins are according    to DIN standards & all the loading/unloading is done mechanically.

• Assist the Parties in arriving at an amicable settlement of disputes, should the need arise. Such disputes    arise mainly on handing over of land and existing facilities by the client to the concessionaire.

• Review matters related to safety and environment management.

PROJECT 2:

Detailed Project Report For Solid Waste Management For Ranchi City, Ranchi Municipal Corporation, Jharkhand, India

Ranchi Municipal Corporation is providing civic services to an estimated population of 10 lakhs of citizen in this capital city of Jharkhand. The project area covers 37 municipal wards spread over in area about 176 sq.km. The long term goal of this project is to improve the civic condition and quality of life of the community in the Jharkhand City by increasing the environmental health and institutional status with viable integrated solid waste management system.

Consultant was responsible for

• Projection of Population for design year.
• Assessment of existing quantum of MSW and expected load for the design year.
• Evaluation of the existing system of collection.
• Transportation & disposal of MSW.
• Categorisation of waste & existing system of collection & Transportation.
• Design of the improved system of collection, transportation & disposal of MSW.
• Design of Sanitary Landfill and design of composting plant.
• Reuse & Recycle technology options.
• Improvements required in the Institutional set-up and legal provisions to improve the efficiency of work in    local bodies.
• Preparation of drawings, design, estimate and Tender document.
• Operation and Maintenance (PO&M) Programmes.
• Devise a self sustainable model of Public Private Partnership (PPP) Model for Solid Waste Management.

PROJECT 3:

Preparation of Detailed Project Report for Solid Waste Management for Jamshedpur City, Jharkhand, India

Jamshedpur Municipal Corporation is providing civic services to an estimated population of 10 lakhs of citizen, in steel city of Jharkhand. The project area covers approximately 150 sq. The long term goal of this project is to improve the civic condition and quality of life of the community in the Jamshedpur city, by increasing the environmental health and institutional status with viable integrated solid waste management system. Hence District Administration, Jamshedpur has engaged Consultant to prepare DPR on Solid Waste Management System.

Consultant was responsible for

• Projection of Population for design year.
• Assessment of existing quantum of MSW and expected load for the design year.
• Evaluation of the existing system of collection.
• Transportation & disposal of MSW.
• Categorisation of waste & existing system of collection & Transportation.
• Design of the improved system of collection, transportation & disposal of MSW.
• Design of Sanitary Landfill and design of composting plant.
• Reuse & Recycle technology options.
• Improvements required in the Institutional set-up and legal provisions to improve the efficiency of work in    local bodies.
• Preparation of drawings, design, estimate and Tender document.
• Operation and Maintenance (O&M) Programmes.
• Devise a self sustainable model of Public Private Partnership (PPP) Model for Solid Waste Management    System in accordance with policies and guidelines of Jawaharlal Nehru Urban Renewal Mission (JNNURM).

PROJECT 4:

Preparation of Detailed Project Report for Solid Waste Management for Medninagar, Jharkhand, Jharkhand, India

Medninagar Municipal is providing civic services to an estimated population of 1 lakhs of citizen. The long term goal of this project is to improve the civic condition and quality of life of the community in the Jharkhand City by increasing the environmental health and institutional status with viable integrated solid waste management system. Hence District Administration Medninagar has engaged consultant to prepare DPR on SWM system

Consultant was responsible for

• Projection of Population for design year.
• Assessment of existing quantum of MSW and expected load for the design year.
• Evaluation of the existing system of collection.
• Transportation & disposal of MSW.
• Categorisation of waste & existing system of collection & Transportation.
• Design of the improved system of collection, transportation & disposal of MSW.
• Design of Sanitary Landfill and design of composting plant.
• Reuse & Recycle technology options.
• Improvements required in the Institutional set-up and legal provisions to improve the efficiency of work in    local bodies.
• Preparation of drawings, design, estimate and Tender document.
• Operation and Maintenance (O&M) Programmes.
• Devise a self sustainable model of Public Private Partnership (PPP) Model for Solid Waste Management.

PROJECT 5:

Eklutna Water & Waste Water and Solid Waste Project, Project Cost- US$ 120 Million, Anchorage, Alaska, USA.

Consultant was responsible for

• Inventorization of Waste.
• Categorization & quantification.
• Quality of Waste.
• Collection, Transportation & disposal.
• Disposal Site Identification.
• Reuse and Recycle Technology Options.
• Preparation of Detailed Project Report (DPR).
• Environmental Impact Assessment.
• Public Awareness and Participation.
• PQ Document for Contractor.
• Developed parameters for Technical and Financial Bid Evaluations.
• Evaluating Prequalification Documents for contractors.
• Preparation of Bid-documents.
• Assisted UDAA in Evaluating Tenders and selection of Contractor.
• Developed Procedures for Monitoring, design, construction quality and contract management and dispute.    settlement.
• Construction Management & Supervision.